Dogwood Wastewater Treatment Modification

ABES Engineering was selected to evaluate the existing wastewater treatment plant at Dogwood Village in Memphis, TN. After evaluation, our team recommended the plant be decommissioned. The ABES team developed plans for the decommissioning as well as plans for a new lift station. The scope also included the design of 600 LF of 8” PVC gravity sewer line and 100 LF of 6” force main. ABES was the Engineer of Record for the design and was also responsible for managing the design team and coordinating the county staff.

Overall, ABES evaluated the existing sanitary sewer system, reviewed permit requirements, effluent testing data, flow data, and other information related to the Dogwood Campus plant operation to determine modifications required for the current system to meet current and expected permit requirements.